June 06, 2024 | 14:30 GMT+7

$770 mln proposed to build HCM City - Moc Bai expressway

Anh Tú -

The 50.9-km expressway connecting the southern city with Moc Bai border gate in Tay Ninh province.

The People’s Committee of Ho Chi Minh City has submitted to the Prime Minister for approval of the investment policy for a project building  the HCM City – Moc Bai expressway (first phase) in the form of Built-Operate-Transfer (BOT).

Total investment capital (for the first phase) is estimated at over VND19.6 trillion ($770 million), with 49.31% to be sourced from the State budget.

The project has a total length of around 50.9 km in the first phase, connecting the southern city with Moc Bai International Border Gate in southern Tay Ninh province, which borders Cambodia.

Under the proposed project, nearly half of the expressway or 24.66 km will run through HCM City.

The expressway will have four lanes with a roadbed width of 25.5 m, allowing a maximum speed of 120 kph.

Construction of the first phase will be divided into four sub-projects and is scheduled to start in June, 2025, and is expected for completion by 2027.

 

Attention
The original article is written and published on VnEconomy in Vietnamese only. To read the full article, please use the Google Translate tool below to translate the content into your preferred language.
VnEconomy is not responsible for the translation.

Google translate