The Ministry of Transport has directed the management boards of three sub-projects in the Eastern North-South Expressway to speed up construction and complete procedures to put them into operation on April 30.
These are the 63.4-km Mai Son - National Highway No. 45, the 100.8-km Vinh Hao - Phan Thiet, and the 99-km Phan Thiet - Dau Giay sub-projects.
The management boards have reported that 92 per cent, 85 per cent, and 91 per cent, respectively, of the sub-projects have been completed.
Leaders from the Ministry of Transport have also regularly examined progress and urged investors in other sub-projects of the Eastern North-South Expressway to work to complete them on schedule.