December 12, 2022 | 11:20

$89mln invested in building Hoa Lien-Tuy Loan expressway section

Ngô Anh Văn

Part of the North-South Expressway, the section runs 11.5 kilometers through central Da Nang city’s Hoa Vang district.

$89mln invested in building Hoa Lien-Tuy Loan expressway section
A section of the Da Nang-Quang Ngai Expressway. Photo: VEC

The Ministry of Transport has approved the construction plan for the Hoa Lien-Tuy Loan section of the North-South Expressway, costing VND2.1 trillion ($89 million).

VND951 billion ($40.3 million) will be spent on site clearance, while construction will cost VND902 billion ($38.3 million).

The section runs 11.5 kilometers entirely within central Da Nang city’s Hoa Vang district.

In the first phase, the link will have four lanes and two emergency stopping lanes, allowing a maximum speed of 80 km/h. The number of lanes will be increased to six in a later phase.

With investment sourced from the State budget, construction is scheduled to kick off in 2023 and is expected to be completed within two years.

Once completed, it will help promote transport links between the La Son-Hoa Lien Expressway and the Da Nang-Quang Ngai Expressway, contributing to enhancing socio-economic development in Da Nang and the surrounding region.

Attention
The original article is written and published on VnEconomy in Vietnamese, then translated into English by Askonomy – an AI platform developed by Vietnam Economic Times/VnEconomy – and published on En-VnEconomy. To read the full article, please use the Google Translate tool below to translate the content into your preferred language.
However, VnEconomy is not responsible for any translation by the Google Translate.

Google translateGoogle translate