Investment in Ninh Binh–Hai Phong expressway raised to $347 million

Nguyen Thuan

The Ninh Binh section of the Ninh Binh–Hai Phong expressway is 25.3 km long, and is built to full four-lane standards with a design speed of 120 kph.

Investment in Ninh Binh–Hai Phong expressway raised to $347 million
Construction of the expressway section running through Ninh Binh province. (Photo: Tien Anh)

The northern Ninh Binh provincial People’s Committee has approved adjustments to the Ninh Binh section of the Ninh Binh–Hai Phong expressway project, increasing the total investment to VND9.113 trillion ($347 million) and expanding the land area required for the project.

The project’s land-use area will increase from approximately 273.57 hectares to 303.62 hectares to accommodate additional technical infrastructure. The additions include three connecting ramps, a bridge overpass structure at the Mai Son interchange and an overpass crossing at the Khanh Duong interchange.

Following the adjustment, the total investment will cover construction costs, compensation and resettlement support, as well as contingency costs. The newly added and revised components are required to be completed by 2028.

The Ninh Binh section of the Ninh Binh–Hai Phong Expressway is 25.3 km long. It starts at the Mai Son interchange in Yen Thang Ward, where it connects with the North–South Expressway, and ends at the bridge crossing the Day River in Khanh Thien Commune.

The expressway will be built to full four-lane standards with a design speed of 120 km per hour.

Attention
The original article is written and published on VnEconomy in Vietnamese, then translated into English by Askonomy – an AI platform developed by Vietnam Economic Times/VnEconomy – and published on En-VnEconomy. To read the full article, please use the Google Translate tool below to translate the content into your preferred language.
However, VnEconomy is not responsible for any translation by the Google Translate.

Google translateGoogle translate