October 22, 2025 | 14:30

Quang Tri reviews progress of T&T Group's key projects valued at over $3.3 bln

Thiên Anh

The Hai Lang LNG Power Plant Project (Phase 1), with a capacity of 1,500 MW and a total investment of over VND53.6 trillion (over $2 billion), is finalizing procedures related to power purchase agreements, site clearance, and forest land use conversion.

Quang Tri reviews progress of T&T Group's key projects valued at over $3.3 bln
The Quang Tri Provincial People's Committee held a working session with T&T Group on October 20.

The Provincial People's Committee of Quang Tri province in central Vietnam held a working session with T&T Group on October 20 to review the progress of the group's key investment projects in the province, with a combined capital exceeding VND87 trillion (approximately $3.3 billion).

According to a report represented at the session, T&T Group is implementing several large-scale projects in Quang Tri.

The Gio Hai Tourism Service Area Project, covering 13.45 ha with a total investment of VND3.69 trillion ($140 million), has completed site clearance. Infrastructure and low-rise constructions are currently underway, with exploitation expected to begin in Q1 2026. The investor has committed to accelerating progress, aiming for completion in Q4 2026.

The Hai Lang LNG Power Plant Project (Phase 1), with a capacity of 1,500 MW and a total investment of over VND53.6 trillion (over $2 billion), is finalizing procedures related to power purchase agreements, site clearance, and forest land use conversion. The province plans to hold a separate meeting in November to resolve difficulties in resettlement work in My Thuy commune. T&T Group affirmed this as a strategic project and will prioritize efforts to operate Unit 1 in Q2 2027 and Unit 2 in Q4 2027.

The 220 kV power transmission line connecting to Savan 1 Wind Power Plant Project has achieved 90% completion in pole erection and is preparing for conductor stringing work, with completion expected in Q4 2025.

Two other major projects which are currently completing investment policy dossiers include the East Dong Ha City Urban Area, with an estimated capital of VND10 trillion (over $379.6 million), and the Cam Lo Complex Urban Area – Resort – Golf Course, with a capital of VND20 trillion (over $759.2 million).

Additionally, the Aviation Industrial – Logistics – Commercial – Service Complex and Airport Urban Area Project is undergoing planning adjustments, while the Quang Tri Airport Project has been urged to accelerate progress for operation by April 30, 2026.

Attention
The original article is written and published on VnEconomy in Vietnamese, then translated into English by Askonomy – an AI platform developed by Vietnam Economic Times/VnEconomy – and published on En-VnEconomy. To read the full article, please use the Google Translate tool below to translate the content into your preferred language.
However, VnEconomy is not responsible for any translation by the Google Translate.

Google translateGoogle translate