Permanent Deputy Prime Minister Pham Gia Tuc has signed the Government's Resolution No 406/NQ-CP, dated November 24, 2026, on the implementation of National Assembly Resolution No. 38/2026/QH16 regarding the investment policy for the Hanoi Capital Region Ring Road 5 Project.
Under the resolution, the Minister of Construction and the chairpersons of the People's Committees of Hanoi, Hai Phong, Bac Ninh, Ninh Binh, Hung Yen, Thai Nguyen, and Phu Tho are responsible for preparing, appraising, and approving feasibility studies for the assigned component projects.
During implementation, the project authorities will continue assessing the feasibility of developing component projects under the public-private partnership (PPP) model in order to mobilize additional non-state funding sources.
The resolution allocates a maximum of nearly VND61.4 trillion (approximately $2.38 billion) from the central government budget for the 2026-2030 period to invest in the 116-km main route of the ring road passing through Hai Phong, Bac Ninh, Ninh Binh, and Hung Yen.
The central budget funding may only be used for construction of the main expressway and cannot be spent on land acquisition, compensation, resettlement, or parallel roads.
The Ministry of Construction has been tasked with coordinating with local authorities to propose funding requirements and disbursement schedules for the expressway component projects. These proposals will be submitted to the Ministry of Finance for consolidation and reporting to the Government and the Prime Minister for inclusion in the 2026-2030 medium-term public investment plan.
The Government also plans to prioritize State budget funding during the 2031-2035 period to continue investing in the project.
Meanwhile, the seven provinces and cities involved must allocate local budget funds for land clearance, compensation, resettlement, and the construction of parallel roads.
Hai Phong, Bac Ninh, Ninh Binh, and Hung Yen have been instructed to prioritize the construction of parallel road sections to ensure smooth local traffic operations when the expressway enters service during the 2026-2030 period.
For the 116-km expressway sections funded by the central budget, local authorities are required to hand over at least 70% of the project land area before September 2027 to facilitate the launch of construction packages that year.
The remaining land must be fully handed over by the second quarter of 2028.
Entire project targeted for completion before 2035
The resolution states that project preparation will begin in 2026, construction will start in 2027, and the entire Ring Road 5 network is expected to be completed before 2035.
For the 116-km expressway sections in Hai Phong, Bac Ninh, Ninh Binh, and Hung Yen, project preparation, appraisal, and approval procedures must be completed by the second quarter of 2027. Construction is scheduled to commence in September 2027, with substantial completion expected by 2030 and commercial operation beginning in 2031.
The remaining component projects are required to be developed and completed in sync with the overall Ring Road 5 project before 2035.