The People's Committee of Ho Chi Minh City has recently approved adjustments to Metro Line 2 project that will run between Ben Thanh and Tham Luong.
According to the adjusted plan, the line will be extended by an additional 200 meters to improve network connectivity.
As a result, the total length of the line will be nearly 11.269 km, including an underground section of about 9.255 km, a transition section of approximately 0.265 km, an elevated section of about 0.846 km, and a ground-level section leading into the depot of 0.903 km.
This is the first metro project to be implemented under special mechanisms and policies outlined by the National Assembly's Resolution No. 188/2025/QH15, dated February 19, 2025, which allows for piloting certain special mechanisms and policies to develop the urban railway network in Hanoi and Ho Chi Minh City.
Google translate